top of page

It's Bank Holiday Weekend!

info908732

We are having some trouble uploading video content to this blog, so please follow us on facebook, where we are sharing video content of the build.


Apologies, we haven't checked in for a while. We have been hard at work in apartments 3, 4, 5 & 6 which are all steadily progressing.


We have started fitting the kitchen in Apartment 4, which has now been fully painted throughout.

The flooring and carpets will be laid this coming week, too!


The plastering is complete in apartment 3, and almost finished in apartment 6.

Apartment 3 will be painted by Wednesday.


Below are some photos of the kitchen which will be fitted to each apartment, plus the shower trays in the house and ensuite bathrooms.







30 views0 comments

Recent Posts

See All

Comments


bottom of page